Urgent Rectifier Transformer Replacement for DLR
The project
Enable Infrastructure (formerly BCM Construction) were instructed by Docklands Light Railway (DLR) to remove two existing rectifier transformers and install two new 2167kVA rectifier transformers at Royal Mint Street as a project variation on a design-and-build basis. The existing transformers had failed and an immediate replacement was necessary to restore a stable supply to DLR’s busiest section of line. As the main framework contractor on three DLR jobs at the time, we were given responsibility for this important project.
The design element of the works consisted of a proposed arrangement drawing, a cable interconnection diagram and the wiring termination schedules. The two projects were set to take place three–four weeks apart, on a seven-day programme, with the isolation and permit-to-work issued on a Thursday morning and the new rectifier transformers commissioned into service the following Thursday. The new rectifier transformers were duly commissioned into service seven days after works commenced, after a 12-hour soak period.
“This site is key to maintaining and supporting the integrity of the railway operation. Enable Infrastructure delivered the works in two text-book operations, on programme and without compromising site or personal safety, despite being under much scrutiny due to potential operational consequences. Great performance all around!”
DLR Project Manager
Prior to the works commencing, DLR/KAD (Keolis Amey Docklands – the networks maintainer) required an approved design, method statement and ITP (Inspection Test Plan) detailing all safety and technical aspects of the works to come. This project variation included: isolation; decommissioning; diversion of power to the generator; removal; installation; pre-commissioning; commissioning and testing of the rectifier transformers into service. Since the spec of the tertiary windings on the new transformers was lower than for the existing transformers, Enable Infrastructure were also instructed to supply and install a temporary back-up generator for essential LV supplies.
The removal and delivery of the rectifier transformers required a road closure on Royal Mint St, and the closure of Cycle Superhighway 3: Enable Infrastructure were required to liaise with Tower Hamlets Council and Transport for London (TfL) to organise this job. It was, in fact, the first major project on DLR since the Poplar Substation fire, which meant it was a major test for the network’s resilience and was extremely time-sensitive.
For the first rectifier transformer, KAD performed the isolation 48 hours before works began to test the network resilience and ensure that peak load times were stable without the rectifier transformer in service. Construction began on Friday morning on both occasions, following site set-up on the Thursday. Prior to the existing transformers’ removal on the Sunday, all cables were disconnected, and alarms/indication wiring tested. Existing HV cable was cut and removed from the existing transformer, and new HV cable installed.
Once the road closure was made effective, the existing transformers were safely removed using a HIAB crane and low-loader. The new transformers were lifted into place and positioned perfectly through the use of pre-drawn markings and a laser level. Both redundant transformers were delivered to the designated storage location for refurbishing.
Works on the newly delivered transformer began with connecting anode cables as well as indication and alarm cables, and re-establishing earth connections. New HV cable was pressure-tested before being terminated on both the transformer and the HV switchboard. All trips and alarms were tested prior to energisation of the new rectifier transformer. The energisation took place on the Wednesday with the assistance of the KAD Senior Authorised Person, and the transformers went on soak for a minimum of 12 hours. During the following shift (on Thursday), the transformers were commissioned into service and load-monitored. There were no issues in the commissioning of either transformer and both are now fully functioning.
The challenge
- The initially accepted programme of works had spanned three weeks, but because of the urgency of the project, this had to be reduced.
- During the transformer lift, the road closure was put in place by a subcontractor, with Cycle Superhighway 3 also closed. There were multiple access points, and some members of the public ignored the signage and moved cones to gain access.
The solution
- Enable Power Systems teams increased resource in order to condense the programme into just seven days for each transformer.
- Enable Infrastructure and the contractor involved halted all work until the problem with the influx of people was resolved. Each individual access point was manned to prevent access until the lift was complete, enabling the works to be carried out safely and without any accidents or further incidents.
The deliverables
- Site set-up, authorised working perimeter located and barriered
- Road closure approval from TfL & Tower Hamlets
- Supply and installation of temporary back-up generator for essential LV supplies
- Design for installation of two rectifier transformers at Royal Mint Street
- Installation of 45m HV cable
- Installation of 150m anode cable
- Removal and delivery of 2 x 2MW rectifier transformers
- Two 2MW transformers fully commissioned into service
- Handover back to DLR/KAD
Gallery
Find out how we can help you
If we can help you in any way, please do get in touch. In order that we can assist you efficiently, please click on the link below. Alternatively, you can call us on 020 7551 0998.
Get in Touch